NOTE! If there are actions connected to an observation, the case will automatically be concluded as soon as deviations are resolved.

  1. Click on observations in menu to the left in the project view
  2. Click on the observation you want to conclude

3. If  you may add a comment (note that you also can add a comment even to closed risk observation)
4. Click on Save

5. Click on mark as concluded. The reporter will automatically receive a notification when you have concluded the observation.